project conversion to different target device

Discussion of application development using iX Developer, including but not limited to getting started, using the functions tab, properties, objects and installation.
Post Reply
ygui003
Posts: 3
Joined: Thu Nov 07, 2013 4:38 pm

project conversion to different target device

Post by ygui003 »

I have created a project for a t4a hmi before, and now I want to update the screen to a t7a, can the project be converted in some way that it could fit a t7a screen?

Thanks

User avatar
Chris T.
Posts: 109
Joined: Mon Nov 20, 2017 5:29 pm

Re: project conversion to different target device

Post by Chris T. »

ygui003,

Yes all you have to do is change your target time in the project settings:

Image

Image
Attachments
Change_Target2.png
Change_Target2.png (41.03 KiB) Viewed 5678 times
Change_Target1.png
Change_Target1.png (37.08 KiB) Viewed 5678 times
Best regards,
Christopher
(801) 708-6690
Technical Support
Contact Us

Beijer Electronics AB
http://www.beijerelectronics.us

Post Reply