I have created a project for a t4a hmi before, and now I want to update the screen to a t7a, can the project be converted in some way that it could fit a t7a screen?

Thanks

User avatar
Chris T.
Posts: 109
Joined: Mon Nov 20, 2017 5:29 pm

Re: project conversion to different target device

Post by Chris T. »

ygui003,

Yes all you have to do is change your target time in the project settings:

Image

Image
Attachments
Change_Target2.png
Change_Target2.png (41.03 KiB) Viewed 5679 times
Change_Target1.png
Change_Target1.png (37.08 KiB) Viewed 5679 times
Best regards,
Christopher